3.The turnstile function testing
3.1 Testing of the turnstile :when there is a signal to open the turnstile, it will be unlocked automatically, and a green arrow will come out to guide the direction.At this time, the pagssengers can pass the turnstile.If there is on one the pass it within the set time ,then the turnstile will be locked automatically.
3.2Testing of the turnstile beam:the beam will fall down when the electricity is cut off. There will be magnetic force if it is electrified, and at this time, you can lift the beam by hand.
4.The matters which should be concerned
4.1 Please do not put any equipment outside of the turnstile,ensure the turnstile can be connected with the ground and ensure the installation in the right way.
4.2 When the equipment is used outdoors, please ensure there is a 100-200mm high cement stage to present the dampness.and fix lookum to prevent the rain. It is forbidden to use the turnstile outddors without any measurements.
5.The connection of the turnstile the connection guide :
1and2 ,left switch , 1 is VDD which should be connected with L1,red threat 2 is COM which should be connected with L2,black threat.
4and5,right switch, 4 is COM which should be connected with L26,black threat 5 is VDD which should be connected with L36 ,red threat
6and7 ,motor,6 is MB which should be connected with L11 ,red threat 7 is MA which should be connected with L13 ,black threat
8and9 ,electrical magnet,8 is LOCK1 which should be connected with L27, blue threat 9 is LOCK2 which should be connected with L28 ,blue threat |